Reports

LogLoon compiles your project data into professional reports—automatically. Set up scheduled reports once, and they’ll be generated and emailed to stakeholders without any manual work.

Report Types

Daily Report

A summary of the day’s activity:

  • Labor hours - Who worked and how many hours (by cost code)
  • Materials - Quantities used or delivered
  • Equipment - Hours of equipment usage
  • Weather - Morning, noon, and evening conditions
  • Notes - Schedule delays, weather impact, accidents/injuries
  • Photos - Progress photos from the day

Progress Report

Shows overall project status:

  • Time progress - Hours used vs. budgeted by cost code
  • Scope progress - Installed vs. budgeted quantities
  • Progress percentages - Visual breakdown of completion
  • Photos - Documentation of current state

Task Report

A snapshot of all project tasks:

  • Tasks grouped by status (Backlog, Ready, In Progress, Blocked, Done)
  • Task details including quantities and assignments
  • Pinned plan locations with thumbnail previews showing where each task is located
  • Optional: task comments and discussion history
  • Configurable filters for which statuses to include

Creating Reports

Manual Reports

  1. Go to your project’s Reports tab
  2. Click + New Daily Report (or Progress/Task Report)
  3. Select the report date
  4. Click Capture Time & Tasks to auto-populate from project data
  5. Add weather, notes, and photos as needed
  6. Click Save Draft or Submit

Selecting a Report Date

The date selector lets you create reports for any date—including past dates. LogLoon accurately reconstructs what happened:

  • Daily Reports: Shows time entries, tasks completed, and weather for that specific date
  • Progress Reports: Shows progress as of that date (budgets vs. actuals at that point in time)
  • Task Reports: Shows the state of all tasks as of that date

This means you can go back and generate a report you forgot to create, or review historical project status at any point.

Auto-Populated Data

When you create a report, LogLoon can automatically pull in:

  • Labor hours from approved time entries for that date
  • Task status from project tasks (current or as of the selected date)
  • Progress data from cost code budgets and actuals
  • Weather from your project’s location (via WeatherAPI)

Automated Reports

Set up scheduled reports to be generated automatically—no manual work required.

Setting Up a Schedule

  1. Go to your project’s Reports tab
  2. Click the Schedule button
  3. Choose the report type
  4. Configure the schedule:
    • Frequency: Daily, Weekly (pick a day), or Monthly (pick a date)
    • Time: When to generate the report (in project timezone)
    • Assignee: Who the report is assigned to

Draft vs. Auto-Submit Mode

ModeWhat Happens
DraftReport is created as a draft for the assignee to review, edit, and manually submit
Auto-SubmitReport is created, submitted, AND emailed to recipients automatically

Email Recipients (Auto-Submit Only)

When using Auto-Submit mode, configure who receives the report:

  • Select team members from your project roster
  • Add external email addresses (comma-separated)
  • Recipients get a professional email with a PDF download link

Report Workflow

Reports move through three statuses:

StatusMeaning
DraftIn progress, can be edited
SubmittedSent for review, assignee notified
ApprovedReviewed and approved by a manager

Managers and Admins can approve submitted reports. Approval is tracked with timestamp and approver name.

Sharing Reports

Export as PDF

  1. Open any report
  2. Click Export PDF
  3. PDF downloads to your device

Filename format: DailyReport_ProjectName_2024-01-15.pdf

Email Delivery

Reports are automatically emailed when:

  • A report is submitted (sent to the assignee)
  • A scheduled report runs in Auto-Submit mode (sent to all configured recipients)

Emails include:

  • PDF download link (valid for 7 days)
  • Direct link to view in LogLoon
  • Project and report details